1. Aug 8, 2002 Demolition underway on old terminal building. |
|
|
|
|
|
|
|
|
|
|
|
|
|
3. Aug 23, 2002. Old terminal building removal complete. |
|
|
|
|
|
|
|
|
|
|
|
|
4. Work underway on new apron section. |
|
|
|
|
|
|
|
|
|
|
|
|
5. Terminal construction begins. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8. Foundation and floor complete Nov 20, 2002. New apron section nears completion. |
|
|
|
|
|
|
|
|
|
|
|
|
9. Nov 28, 2002 Crane positions steel members. |
|
|
|
|
|
|
|
|
|
|
|
|
10. Nov 28, 2002. With new apron section complete (top right), reconstruction of main apron continues. |
|
|
|
|
|
|
|
|
|
|
|
|
|
12. Dec 10, 2002. Main apron sewer installation continues. |
|
|
|
|
|
|
|
|
|
|
|
|
13. Dec 10, 2002 Workers secure the completed steel structure. |
|
|
|
|
|
|
|
|
|
|
|
|
14. Panoramic View Dec 12, 2002 |
|
|
|
|
|
|
|
|
|
|
|
|
15. Dec 12, 2002. Interior concrete block wall assembly underway. |
|
|
|
|
|
|
|
|
|
|
|
|
16. Panoramic Dec 18, 2002. Terminal roof and second floor underway. Main apron sewer installation nears completion. |
|
|
|
|
|
|
|
|
|
|
|
|
17. Jan 16, 2003. Apron work halted until spring. Terminal building continues to take shape. |
|
|
|
|
|
|
|
|
|
|
|
|
18. Feb 13, 2003. Upper concrete floor pored. Initial assembly of metal stud walls. |
|
|
|
|
|
|
|
|
|
|
|
|
|
20. Feb 27, 2003. Upper roof nears completion. |
|
|
|
|
|
|
|
|
|
|
|
|
21. March 15, 2003 The bulk of work on roof completed. Final sheathing applied. |
|
|
|
|
|
|
|
|
|
|
|
|
22. March 15, 2003. Airport Commission continues to experiment with exterior colours. |
|
|
|
|
|
|
|
|
|
|
|
|
23. March 15, 2003. Public access, main entrance. Glass panels partially assembled. |
|
|
|
|
|
|
|
|
|
|
|
|
24. March 27, 2003. View from paking lot. |
|
|
|
|
|
|
|
|
|
|
|
|
|
26. March 27, 2003. Airside view from unfinished terminal apron. |
|
|
|
|
|
|
|
|
|
|
|
|
27. April 25 Glass panels complete. Brick facade nears completion. |
|
|
|
|
|
|
|
|
|
|
|
|
28. April 25. Main apron ready for paving. |
|
|
|
|
|
|
|
|
|
|
|
|
29 May 27 Main Apron paving nears completion. |
|
|
|
|
|
|
|
|
|
|
|
|
30. June 1, 2003 Airside view from paved apron. |
|
|
|
|
|
|
|
|
|
|
|
|
|
32. June 1, 2003 Interior view. |
|
|
|
|
|
|
|
|
|
|
|
|
33. June 1, 2003 Interior view looking toward airside. |
|
|
|
|
|
|
|
|
|
|
|
|
34. June 1, 2003 Interior view, looking back to main entrance and parking lot. |
|
|
|
|
|
|
|
|
|
|
|
|
35. July 26, 2003 Front entrance curbs go in. |
|
|
|
|
|
|
|
|
|
|
|
|
36. July 26, 2003. Error in grading Main Apron requires addition work. |
|
|
|
|
|
|
|
|
|
|
|
|
37. August 13, 2003 Panoramic view from Main Apron to front parking lot. |
|
|
|
|
|
|
|
|
|
|
|
|
38. August 18, 2003 Finishing touches to roof with front entrance paving beginning. |
|
|
|
|
|
|
|
|
|
|
|
|
39. August 24, 2003 If you build it....... |
|
|
|
|
|
|
|
|
|
|
|
|
40. August 24, 2003 Inbound from Dusseldorf. Outbound executive service for Guelph. |
|
|
|
|
|
|
|
|
|
|
|
|
41. June 4, 2004 construction of a 5th apron underway. Project to include a stream relocation |
|
|
|
|
|
|
|
|
|
|
|
|
42. July 22, 2004 Land leveling continues |
|
|
|
|
|
|
|
|
|
|
|
|
43. August 1, 2004. Newly dug stream nears completion. Airport access road lowered. |
|
|
|
|
|
|
|
|
|
|
|
|
44. August 21, 2004. Stream diverted. Old stream filled in. Aviation Day. |
|
|
|
|
|
|
|
|
|
|
|
|
45. September 12, 2004. Hydro roughed in. New taxiways take shape. |
|
|
|
|
|
|
|
|
|
|
|
|
|
47. October 11, 2004. Looking northeast from the western edge of construction. |
|
|
|
|
|
|
|
|
|
|
|
|
48. October 11, 2004. Security fence starts going in around new Apron (4). |
|
|
|
|
|
|
|
|
|
|
|
|
49. Oct 12, 2004. Twenty one building lots. Large hangars will use more than one lot. |
|
|
|
|
|
|
|
|
|
|
|
|
50. Nov 19, 2004. Paving new taxiways, new south field access road, and main airport access road. |
|
|
|
|
|
|
|
|
|
|
|
|
51. Nov 19, 2004. Capital Paving Ltd at work on new taxiway. |
|
|
|
|
|
|
|
|
|
|
|
|
52. Dec 3, 2004. Construction vehicles gone. Ready for building now. |
|
|
|
|
|
|
|
|
|
|
|
|
53. Sep 20, 2005. New walkways added, and new underground lines laid for expansion. |
|
|
|
|
|
|
|
|
|
|
|
|
54. Sep 20, 2005. Storage facility nears completion on south end of field beside maintenance garage |
|
|
|
|
|
|
|
|
|
|
|
|
55. Sep 22, 2005. North end of Treminal readied for minor expansion.
|
|
|
|
|
|
|
|
|
|
|
|
|
56. Sep 28, 2005. Work continues with concrete foundation forms readied. |
|
|
|
|
|
|
|
|
|
|
|
|
57. Oct 3, 2005. Foundation ready. |
|
|
|
|
|
|
|
|
|
|
|
|
58. Oct 17, 2005 Wall framing underway. |
|
|
|
|
|
|
|
|
|
|
|
|
59. Oct 17, 2005. New additional parking area prepared for paving. |
|
|
|
|
|
|
|
|
|
|
|
|
60. Nov 14, 2005 Exterior takes shape. |
|
|
|
|
|
|
|
|
|
|
|
|
61. Nov 14, 2005. New parking area paving complete. |
|
|
|
|
|
|
|
|
|
|
|
|
62. January 12, 2006. New parking areas being put to good use. |
|
|
|
|
|
|
|
|
|
|
|
|
63. June 6, 2007 Paving completed on Apron 4 |
|
|
|
|
|
|
|
|
|
|
|
|
64. Oct 11, 2007. Construction started on new parking lot, and two hangars for Apron 4 |
|
|
|
|
|
|
|
|
|
|
|
|
65. Nov 3, 2007 Parking lot paving completed. Hangar work continues. |
|
|
|
|
|
|
|
|
|
|
|
|
66. Nov 6, 2007 Main apron expanded to accomodate aircraft handling equipment. |
|
|
|
|
|
|
|
|
|
|
|
|
67. Nov 16, 2007 Paving main apron extension area. |
|
|
|
|
|
|
|
|
|
|
|
|
68. Nov 16, 2007 Hangar work progressing. Parking lot ready for painting. |
|
|
|
|
|
|
|
|
|
|
|
|
69. Jan 18, 2008. Building a new domestic arrival entrance. |
|
|
|
|
|
|
|
|
|
|
|
|
70. Jan 18, 2008. Third hangar on Apron 4 erected. |
|
|
|
|
|
|
|
|
|
|
|
|
71. May 27, 2008 Construction begins on the new Bravo taxiway, moving it closer to runway 32. |
|
|
|
|
|
|
|
|
|
|
|
|
72. June 5, 2008. Machinery attacks Charlie taxiway between runway 07 and Apron 2 for a complete rebuild. |
|
|
|
|
|
|
|
|
|
|
|
|
73. June 15, 2008. Charlie taxi ready for paving. Car parking spaces sacrificed to build new executive aircraft parking area. |
|
|
|
|
|
|
|
|
|